Dept. of Trans. PROGRESS Serial No. Contract No. 19-238-08-27 08-1E7204 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 87% Location: Federal Project: 08-RIV-10-80.0/156.4 NONE 08-RIV-91 08-SBD-10 08-SBD-15 Progress payment No. 001 Payment period ending: 08-20-19 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 255,268.80 255,268.80 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 255,268.80 255,268.80 5. Mobilization 52,250.00 52,250.00 6. Total Work Completed 307,518.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -25,526.88 -25,526.88 c. Reduction after 95% Comp. 9. Total pay to Contractor 281,991.92 281,991.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 281,991.92