Dept. of Trans. PROGRESS Serial No. Contract No. 21-358-09-40 08-1E8404 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 47% Location: Federal Project: 08-RIV-62-R6.7/9.2 ACNH-P062(46) 08-SBD-62-29.3/33.6 08-SBD-62-0.0/15.1 Progress payment No. 009 Payment period ending: 12-20-21 MATICH CORPORATION PO BOX 10 HIGHLAND CA 92346 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,047,588.32 1,113,655.72 2. a. Extra Work 133,868.50 -55,061.55 b. Adustment Comp. 605,000.00 405,000.00 3. Materials on Hand 4. Earned Subject to Retention 13,786,456.82 1,463,594.17 5. Mobilization 211,240.90 0.00 6. Total Work Completed 13,997,697.72 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,997,697.72 1,463,594.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,463,594.17