Dept. of Trans. PROGRESS Serial No. Contract No. 19-143-14-52 08-1E8504 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 100% Location: Federal Project: 08-SBD-142-0.0/5.7 1BST-P142(18) Progress payment No. 002 Payment period ending: 05-20-19 ALL AMERICAN ASPHALT 400 E 6TH ST CORONA CA 92878 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 179,805.65 156,114.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 179,805.65 156,114.50 5. Mobilization 6. Total Work Completed 179,805.65 7. Deductions -8,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -17,980.57 -15,611.45 c. Reduction after 95% Comp. 9. Total pay to Contractor 153,825.08 136,503.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 136,503.05