Dept. of Trans. PROGRESS Serial No. Contract No. 21-054-15-36 08-1F13U4 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 72% Location: Federal Project: 08-SBD-62-122.0/142.7 NONE 08-SBD-95-9.7/33.6 Progress payment No. 007 Payment period ending: 02-20-21 GRANITE CONSTRUCTION COMPANY 38000 MONROE ST INDIO CA 92203 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,573,759.73 72,310.00 2. a. Extra Work 214,960.51 86,693.14 b. Adustment Comp. 329,459.50 30,108.08 3. Materials on Hand 4. Earned Subject to Retention 19,118,179.74 189,111.22 5. Mobilization 1,955,652.00 0.00 6. Total Work Completed 21,073,831.74 7. Deductions -20,000.00 -8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,053,831.74 181,111.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 181,111.22