Dept. of Trans. PROGRESS Serial No. Contract No. 20-147-10-16 08-1F1424 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 20% Location: Federal Project: 08-RIV-15-23.9/33.4 B1IM-015-1(248) Progress payment No. 004 Payment period ending: 05-20-20 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,432,102.02 1,579,865.75 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 72,861.47 -86,737.51 4. Earned Subject to Retention 2,504,963.49 1,493,128.24 5. Mobilization 900,000.00 300,000.00 6. Total Work Completed 3,332,102.02 7. Deductions -10,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,394,963.49 1,790,128.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,790,128.24