Dept. of Trans. PROGRESS Serial No. Contract No. 20-174-09-14 08-1F1424 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 24% Location: Federal Project: 08-RIV-15-23.9/33.4 B1IM-015-1(248) Progress payment No. 005 Payment period ending: 06-20-20 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,333,098.35 2,900,996.33 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 70,562.65 -2,298.82 4. Earned Subject to Retention 5,403,661.00 2,898,697.51 5. Mobilization 1,140,000.00 240,000.00 6. Total Work Completed 6,473,098.35 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,533,661.00 3,138,697.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,138,697.51