Dept. of Trans. PROGRESS Serial No. Contract No. 21-237-12-36 08-1F1424 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 79% Location: Federal Project: 08-RIV-15-23.9/33.4 B1IM-015-1(248) Progress payment No. 019 Payment period ending: 08-20-21 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,904,053.47 123,925.74 2. a. Extra Work 110,037.80 0.00 b. Adustment Comp. 219.27 0.00 3. Materials on Hand 4. Earned Subject to Retention 14,014,310.54 123,925.74 5. Mobilization 1,200,000.00 0.00 6. Total Work Completed 15,214,310.54 7. Deductions -34,000.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,180,310.54 143,925.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 143,925.74