Dept. of Trans. PROGRESS Serial No. Contract No. 21-235-15-29 08-1F1434 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 34% Location: Federal Project: 08-RIV-15-38.2/51.5 ACIM-015(166) Progress payment No. 007 Payment period ending: 08-20-21 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,528,177.80 1,423,380.06 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 453,998.29 -45,411.71 4. Earned Subject to Retention 9,982,176.09 1,377,968.35 5. Mobilization 1,681,500.00 0.00 6. Total Work Completed 11,209,677.80 7. Deductions -20,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,643,676.09 1,367,968.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,367,968.35