Dept. of Trans. PROGRESS Serial No. Contract No. 21-263-14-43 08-1F1434 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 40% Location: Federal Project: 08-RIV-15-38.2/51.5 ACIM-015(166) Progress payment No. 008 Payment period ending: 09-20-21 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,962,127.17 433,949.37 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 320,772.51 -133,225.78 4. Earned Subject to Retention 10,282,899.68 300,723.59 5. Mobilization 1,681,500.00 0.00 6. Total Work Completed 11,643,627.17 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,954,399.68 310,723.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 310,723.59