Dept. of Trans. PROGRESS Serial No. Contract No. 22-236-08-32 08-1F1434 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 73% Location: Federal Project: 08-RIV-15-38.2/51.5 ACIM-015(166) Progress payment No. 019 Payment period ending: 08-20-22 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,795,756.81 310,407.92 2. a. Extra Work 260,521.07 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -9,693.87 4. Earned Subject to Retention 20,056,277.88 300,714.05 5. Mobilization 1,770,000.00 0.00 6. Total Work Completed 21,826,277.88 7. Deductions -22,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,804,277.88 298,714.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 298,714.05