Dept. of Trans. PROGRESS Serial No. Contract No. 15-057-08-56 08-1F3104 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 47% Location: Federal Project: 08-SBD-0-0.0 NH- Progress payment No. 001 Payment period ending: 02-19-15 O'DONNELL CONSTRUCTION INC. 559 W. COVINA BLVD. SAN DIMAS, CA 91773-2911 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 84,427.25 84,427.25 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 84,427.25 84,427.25 5. Mobilization 6. Total Work Completed 84,427.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 84,427.25 84,427.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 84,427.25