Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-309-14-38 08-1F4704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-178-0.0/14.8 NONE Progress payment No. 003 Payment period ending: 10-16-15 GRIFFITH COMPANY 3050 E BIRCH STREET BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,016,946.63 1,375,836.65 2. a. Extra Work 29,121.22 16,394.47 b. Adustment Comp. -284.47 -284.47 3. Materials on Hand 4. Earned Subject to Retention 3,045,783.38 1,391,946.65 5. Mobilization 6. Total Work Completed 3,045,783.38 7. Deductions -10,100.00 -10,100.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,035,683.38 1,381,846.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,381,846.65