Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 22-109-12-49 08-1F5904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-RIV-74-36.9/43.6 ACNH-P074(70) Progress payment No. 012 Payment period ending: 03-25-22 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,166,655.79 -40,209.90 2. a. Extra Work 35,824.64 23,266.96 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,202,480.43 -16,942.94 5. Mobilization 50,000.00 0.00 6. Total Work Completed 2,252,480.43 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,252,480.43 -16,942.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -16,942.94