Dept. of Trans. PROGRESS Serial No. Contract No. 20-325-08-18 08-1F6904 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 97% Location: Federal Project: 08-RIV-79-0.0/15.6 NONE Progress payment No. 008 Payment period ending: 11-20-20 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,393,449.30 145,665.74 2. a. Extra Work 39,094.84 4,692.00 b. Adustment Comp. -353,398.93 54,610.74 3. Materials on Hand 4. Earned Subject to Retention 7,079,145.21 204,968.48 5. Mobilization 225,200.00 0.00 6. Total Work Completed 7,304,345.21 7. Deductions -12,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,292,345.21 194,968.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 194,968.48