Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 21-077-07-37 08-1F6904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-RIV-79-0.0/15.6 NONE Progress payment No. 011 Payment period ending: 02-19-21 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,409,253.38 4,750.00 2. a. Extra Work 113,617.23 1,370.34 b. Adustment Comp. -362,171.29 -8,772.36 3. Materials on Hand 4. Earned Subject to Retention 7,160,699.32 -2,652.02 5. Mobilization 225,200.00 0.00 6. Total Work Completed 7,385,899.32 7. Deductions -10,000.00 3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,375,899.32 347.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 347.98