Dept. of Trans. SEMI-FINAL Serial No. Contract No. 21-109-09-02 08-1F6904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-RIV-79-0.0/15.6 NONE Progress payment No. 012 Payment period ending: 02-19-21 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,414,633.16 5,379.78 2. a. Extra Work 117,012.62 3,395.39 b. Adustment Comp. -362,171.29 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,169,474.49 8,775.17 5. Mobilization 225,200.00 0.00 6. Total Work Completed 7,394,674.49 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,384,674.49 8,775.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,775.17