Dept. of Trans. PROGRESS Serial No. Contract No. 18-086-13-16 08-1F8404 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 19% Location: Federal Project: 08-RIV-111-0.0/18.3 SSTG-P111(76) Progress payment No. 001 Payment period ending: 03-20-18 CAL STRIPE INC 2040 E STEEL RD COLTON CA 92324 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 215,116.00 215,116.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 215,116.00 215,116.00 5. Mobilization 46,107.30 46,107.30 6. Total Work Completed 261,223.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 261,223.30 261,223.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 261,223.30