Dept. of Trans. PROGRESS Serial No. Contract No. 18-142-13-41 08-1F8504 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 23% Location: Federal Project: 08-RIV-371-60.2/77.1 SSTG-S371(9) Progress payment No. 001 Payment period ending: 05-20-18 JABRE CONTRACTING INC 1813 MANZANITA LN MANHATTAN BEACH CA 90266 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 488,053.91 488,053.91 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 488,053.91 488,053.91 5. Mobilization 50,000.00 50,000.00 6. Total Work Completed 538,053.91 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 538,053.91 538,053.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 538,053.91