Dept. of Trans. PROGRESS Serial No. Contract No. 17-331-16-19 08-1F9604 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 9% Location: Federal Project: 08-SBD-15-7.5/7.5 NONE Progress payment No. 003 Payment period ending: 11-19-17 KANAAN CONSTRUCTION INC 1438 ARROW HWY #I IRWINDALE CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 118,608.00 116,358.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 51,000.00 0.00 4. Earned Subject to Retention 169,608.00 116,358.00 5. Mobilization 6. Total Work Completed 118,608.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 169,608.00 116,358.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 116,358.00