Dept. of Trans. PROGRESS Serial No. Contract No. 18-025-10-05 08-1F9604 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 36% Location: Federal Project: 08-SBD-15-7.5/7.5 NONE Progress payment No. 005 Payment period ending: 01-18-18 KANAAN CONSTRUCTION INC 230 S IRWINDALE AVE AZUSA CA 91702 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 160,448.00 12,100.00 2. a. Extra Work 7,092.00 3,152.00 b. Adustment Comp. 3. Materials on Hand 51,000.00 0.00 4. Earned Subject to Retention 218,540.00 15,252.00 5. Mobilization 6. Total Work Completed 167,540.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 218,540.00 15,252.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,252.00