Dept. of Trans. PROGRESS Serial No. Contract No. 18-115-14-19 08-1G2304 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 100% Location: Federal Project: 08-SBD-15-76.8/154.7 NONE Progress payment No. 005 Payment period ending: 12-20-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 507,686.24 0.00 2. a. Extra Work 36,831.39 36,831.39 b. Adustment Comp. 63,652.83 63,652.83 3. Materials on Hand 4. Earned Subject to Retention 608,170.46 100,484.22 5. Mobilization 50,000.00 0.00 6. Total Work Completed 658,170.46 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions -10,048.42 -10,048.42 c. Reduction after 95% Comp. 9. Total pay to Contractor 638,122.04 90,435.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 90,435.80