Dept. of Trans. PROGRESS Serial No. Contract No. 24-052-12-32 08-1G2804 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 79% Location: Federal Project: 08-SBD-18-95.4/95.4 NONE Progress payment No. 008 Payment period ending: 02-20-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 676,525.00 125,099.00 2. a. Extra Work 105,386.64 16,497.80 b. Adustment Comp. -16,981.25 0.00 3. Materials on Hand 4. Earned Subject to Retention 764,930.39 141,596.80 5. Mobilization 68,900.00 3,445.00 6. Total Work Completed 833,830.39 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -14,159.68 -14,159.68 c. Reduction after 95% Comp. 9. Total pay to Contractor 819,670.71 130,882.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 130,882.12