Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 24-163-08-38 08-1G2804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-18-95.4/95.4 NONE Progress payment No. 012 Payment period ending: 04-29-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,152,497.85 -30,800.00 2. a. Extra Work 162,095.16 15,492.10 b. Adustment Comp. -25,284.98 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,289,308.03 -15,307.90 5. Mobilization 68,900.00 0.00 6. Total Work Completed 1,358,208.03 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,358,208.03 -15,307.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -15,307.90