Dept. of Trans. PROGRESS Serial No. Contract No. 16-117-15-18 08-1G5604 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 90% Location: Federal Project: 08-SBD-210-2.6/4.9 NONE 08-SBD-15-6.0/6.0 Progress payment No. 003 Payment period ending: 04-20-16 STL LANDSCAPE INC 8122 COMPTON AVE LOS ANGELES CA 90001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 229,760.22 16,996.59 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 229,760.22 16,996.59 5. Mobilization 6. Total Work Completed 229,760.22 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 6,109.94 c. Reduction after 95% Comp. 9. Total pay to Contractor 229,760.22 23,106.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,106.53