Dept. of Trans. PROGRESS Serial No. Contract No. 16-266-11-59 08-1G5704 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 100% Location: Federal Project: 08-SBD-10-3.3/6.7 NONE 08-RIV-15-41.3/41.3 Progress payment No. 007 Payment period ending: 09-16-16 DIVERSIFIED LANDSCAPE COMPANY 21730 BUNDY CANYON RD WILDOMAR CA 92595 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 758,873.49 56,618.94 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 758,873.49 56,618.94 5. Mobilization 6. Total Work Completed 758,873.49 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 753,873.49 56,618.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 56,618.94