Dept. of Trans. PROGRESS Serial No. Contract No. 25-353-14-06 08-1G6304 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 86% Location: Federal Project: 08-RIV-111-47.2/55.3 ACNH-P111(80) Progress payment No. 009 Payment period ending: 12-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,128,754.83 65,168.75 2. a. Extra Work 142,297.29 0.00 b. Adustment Comp. -231,540.21 0.00 3. Materials on Hand 4. Earned Subject to Retention 11,039,511.91 65,168.75 5. Mobilization 1,300,000.00 0.00 6. Total Work Completed 12,339,511.91 7. Deductions -24,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,315,511.91 65,168.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 65,168.75