Dept. of Trans. PROGRESS Serial No. Contract No. 25-022-10-59 08-1G8804 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 87% Location: Federal Project: 08-SBD-15-6.7/R22.3 ACIM-015(1) Progress payment No. 015 Payment period ending: 01-20-25 LANDSCAPE SUPPORT SERVICES INC 12610 SATICOY ST SOUTH N HOLLYWOOD CA 91605 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,960,477.51 100,359.45 2. a. Extra Work 356,811.22 52,278.26 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 11,317,288.73 152,637.71 5. Mobilization 949,748.00 0.00 6. Total Work Completed 12,267,036.73 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,267,036.73 152,637.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 152,637.71