Dept. of Trans. PROGRESS Serial No. Contract No. 24-114-10-19 08-1H0604 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 39% Location: Federal Project: 08-RIV-74-34.3/45.1 ACNH-P074(72) Progress payment No. 009 Payment period ending: 04-20-24 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,811,416.29 790,261.69 2. a. Extra Work 972,161.35 18,100.38 b. Adustment Comp. 3. Materials on Hand 111,836.27 53,476.71 4. Earned Subject to Retention 8,895,413.91 861,838.78 5. Mobilization 2,422,500.00 0.00 6. Total Work Completed 11,206,077.64 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,317,913.91 861,838.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 861,838.78