Dept. of Trans. PROGRESS Serial No. Contract No. 24-149-11-04 08-1H0604 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 45% Location: Federal Project: 08-RIV-74-34.3/45.1 ACNH-P074(72) Progress payment No. 011 Payment period ending: 05-20-24 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,948,532.85 3,137,116.56 2. a. Extra Work 1,518,236.32 319,088.55 b. Adustment Comp. 3. Materials on Hand 176,836.27 65,000.00 4. Earned Subject to Retention 12,643,605.44 3,521,205.11 5. Mobilization 2,422,500.00 0.00 6. Total Work Completed 14,889,269.17 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,066,105.44 3,521,205.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,521,205.11