Dept. of Trans. FINAL Serial No. Contract No. 20-157-15-22 08-1H0904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-RIV-15-43.5/43.5 NONE Progress payment No. 010 Payment period ending: 11-14-19 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 810,291.49 0.00 2. a. Extra Work 4,957.28 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 815,248.77 0.00 5. Mobilization 6. Total Work Completed 815,248.77 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 815,248.77 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00