Dept. of Trans. PROGRESS Serial No. Contract No. 23-082-10-33 08-1H2004 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 9% Location: Federal Project: 08-RIV-10-R92.9/R101.1 ACIM-010(4) Progress payment No. 003 Payment period ending: 03-20-23 AMES CONSTRUCTION INC 2000 AMES DR BURNSVILLE MN 55306 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 482,319.00 367,435.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 31,941.00 31,941.00 4. Earned Subject to Retention 514,260.00 399,376.00 5. Mobilization 325,000.00 325,000.00 6. Total Work Completed 807,319.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 839,260.00 724,376.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 724,376.00