Dept. of Trans. PROGRESS Serial No. Contract No. 23-325-01-54 08-1H2004 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 39% Location: Federal Project: 08-RIV-10-R92.9/R101.1 ACIM-010(4) Progress payment No. 011 Payment period ending: 11-20-23 AMES CONSTRUCTION INC 2500 COUNTY RD 42 W BURNSVILLE MN 55337 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,441,007.32 324,609.22 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 67,963.77 -14,652.30 4. Earned Subject to Retention 3,508,971.09 309,956.92 5. Mobilization 650,000.00 32,500.00 6. Total Work Completed 4,091,007.32 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,158,971.09 342,456.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 342,456.92