Dept. of Trans. PROGRESS Serial No. Contract No. 24-052-12-49 08-1H2004 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 49% Location: Federal Project: 08-RIV-10-R92.9/R101.1 ACIM-010(4) Progress payment No. 014 Payment period ending: 02-20-24 AMES CONSTRUCTION INC 2500 COUNTY RD 42 W BURNSVILLE MN 55337 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,654,389.82 374,139.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 53,503.40 -14,460.37 4. Earned Subject to Retention 4,707,893.22 359,678.63 5. Mobilization 650,000.00 0.00 6. Total Work Completed 5,304,389.82 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,357,893.22 359,678.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 359,678.63