Dept. of Trans. FINAL Serial No. Contract No. 19-002-10-49 08-1H2204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-VAR NONE Progress payment No. 006 Payment period ending: 09-27-18 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 492,783.81 0.00 2. a. Extra Work 18,312.18 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 511,095.99 0.00 5. Mobilization 35,600.00 0.00 6. Total Work Completed 546,695.99 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 546,695.99 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00