Dept. of Trans. PROGRESS Serial No. Contract No. 19-022-13-05 08-1H2304 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 78% Location: Federal Project: 08-SBD-15-2.5/3.8 NONE Progress payment No. 006 Payment period ending: 01-20-19 J MCLOUGHLIN ENGINEERING CO INC 10641 FULTON CT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 711,534.94 13,300.00 2. a. Extra Work 3,918.30 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 715,453.24 13,300.00 5. Mobilization 95,000.00 0.00 6. Total Work Completed 810,453.24 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 808,453.24 13,300.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,300.00