Dept. of Trans. FINAL Serial No. Contract No. 17-220-08-46 08-1H2804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-215-2.6/2.6 NONE Progress payment No. 006 Payment period ending: 09-29-16 RIVERSIDE CONSTRUCTION CO INC PO BOX 1146 RIVERSIDE CA 925021146 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,146.00 0.00 2. a. Extra Work 211,309.58 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 212,455.58 0.00 5. Mobilization 6. Total Work Completed 212,455.58 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 212,455.58 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00