Dept. of Trans. PROGRESS Serial No. Contract No. 21-203-12-06 08-1H2904 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 8% Location: Federal Project: 08-SBD-173-18.6/18.7 ACST-S173(4) Progress payment No. 003 Payment period ending: 07-20-21 STRONGHOLD ENGINEERING INCORPORATED 150 W WALNUT AVE PERRIS CA 92571 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 228,680.20 94,941.60 2. a. Extra Work 1,000.00 1,000.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 229,680.20 95,941.60 5. Mobilization 6. Total Work Completed 229,680.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 229,680.20 95,941.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 95,941.60