Dept. of Trans. PROGRESS Serial No. Contract No. 22-172-08-34 08-1H3414 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 100% Location: Federal Project: 08-SBD-259-0.0/1.5 ACNH-X071(73) 08-SBD-215-4.1/10.6 08-SBD-210-21.1/32.4 Progress payment No. 011 Payment period ending: 06-20-22 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,688,444.64 704,435.86 2. a. Extra Work 59,742.29 23,100.21 b. Adustment Comp. 702,535.20 552,535.32 3. Materials on Hand 4. Earned Subject to Retention 6,450,722.13 1,280,071.39 5. Mobilization 153,370.00 0.00 6. Total Work Completed 6,604,092.13 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,604,092.13 1,280,071.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,280,071.39