Dept. of Trans. PROGRESS Serial No. Contract No. 17-235-15-28 08-1H3714 PROGRESS PAYMENT VOUCHER %complete: %time: 24% 100% Location: Federal Project: 08-SBD-15-14.7/32.5 NONE Progress payment No. 008 Payment period ending: 08-18-17 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 543,554.55 39,432.62 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 543,554.55 39,432.62 5. Mobilization 6. Total Work Completed 543,554.55 7. Deductions -6,410.35 -3,410.35 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 537,144.20 36,022.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,022.27