Dept. of Trans. PROGRESS Serial No. Contract No. 20-023-07-31 08-1H5304 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 19% Location: Federal Project: 08-RIV-15 B1ST-000C(491) 08-SBD-210-0.1/0.1 08-RIV-10 08-SBD-60 Progress payment No. 002 Payment period ending: 01-20-20 SELECT ELECTRIC INC 2790 BUSINESS PARK DR VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 335,642.90 201,851.81 2. a. Extra Work 4,412.67 4,412.67 b. Adustment Comp. 3. Materials on Hand 105,702.00 0.00 4. Earned Subject to Retention 445,757.57 206,264.48 5. Mobilization 176,742.00 58,914.00 6. Total Work Completed 516,797.57 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 612,499.57 255,178.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 255,178.48