Dept. of Trans. PROGRESS Serial No. Contract No. 20-057-08-11 08-1H6604 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 64% Location: Federal Project: 08-SBD-15-R107.4/R107.4 NONE 08-SBD-15-161.2/161.2 Progress payment No. 003 Payment period ending: 02-20-20 KANAAN CONSTRUCTION INC 230 S IRWINDALE AVE AZUSA CA 91702 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 586,172.50 236,227.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 586,172.50 236,227.50 5. Mobilization 60,000.00 3,000.00 6. Total Work Completed 646,172.50 7. Deductions -10,000.00 43,435.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 636,172.50 282,662.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 282,662.50