Dept. of Trans. PROGRESS Serial No. Contract No. 20-114-10-16 08-1H6604 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 68% Location: Federal Project: 08-SBD-15-R107.4/R107.4 NONE 08-SBD-15-161.2/161.2 Progress payment No. 005 Payment period ending: 04-20-20 KANAAN CONSTRUCTION INC 230 S IRWINDALE AVE AZUSA CA 91702 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 627,849.70 27,181.20 2. a. Extra Work 38,407.01 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 666,256.71 27,181.20 5. Mobilization 60,000.00 0.00 6. Total Work Completed 726,256.71 7. Deductions 0.00 13,225.75 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 726,256.71 40,406.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 40,406.95