Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-222-09-34 08-1H7904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-215-7.5/7.6 NONE Progress payment No. 002 Payment period ending: 05-03-17 BEAR VALLEY PAVING A CALIFORNIA CORPORATION 41841 GARSTIN DRIVE BIG BEAR LAKE CA 92315 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 157,495.65 5,981.25 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 157,495.65 5,981.25 5. Mobilization 6. Total Work Completed 157,495.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 157,495.65 5,981.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,981.25