Dept. of Trans. SEMI-FINAL Serial No. Contract No. 22-025-11-40 08-1H9004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-62-106.0/142.3 NONE 08-SBD-95-0.0/9.7 Progress payment No. 007 Payment period ending: 05-19-21 JAZZAR CONSTRUCTION GROUP INC 192 TECHNOLOGY DR #M IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,879,726.75 0.00 2. a. Extra Work 23,172.87 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,902,899.62 0.00 5. Mobilization 105,000.00 0.00 6. Total Work Completed 3,007,899.62 7. Deductions -135,063.49 12,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,872,836.13 12,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,000.00