Dept. of Trans. PROGRESS Serial No. Contract No. 24-355-05-41 08-1H9914 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 52% Location: Federal Project: 08-VAR SSTG-000C(554) Progress payment No. 006 Payment period ending: 12-20-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,349,173.25 174,296.75 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 284,818.13 -23,237.45 4. Earned Subject to Retention 1,633,991.38 151,059.30 5. Mobilization 190,000.00 0.00 6. Total Work Completed 1,539,173.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,823,991.38 151,059.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 151,059.30