Dept. of Trans. PROGRESS Serial No. Contract No. 25-055-11-16 08-1H9914 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 65% Location: Federal Project: 08-VAR SSTG-000C(554) Progress payment No. 008 Payment period ending: 02-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,865,719.25 313,217.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 203,469.88 -51,217.25 4. Earned Subject to Retention 2,069,189.13 261,999.75 5. Mobilization 200,000.00 0.00 6. Total Work Completed 2,065,719.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,269,189.13 261,999.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 261,999.75