Dept. of Trans. PROGRESS Serial No. Contract No. 25-079-15-02 08-1H9914 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 72% Location: Federal Project: 08-VAR SSTG-000C(554) Progress payment No. 009 Payment period ending: 03-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,179,727.25 314,008.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 144,412.58 -59,057.30 4. Earned Subject to Retention 2,324,139.83 254,950.70 5. Mobilization 200,000.00 0.00 6. Total Work Completed 2,379,727.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,524,139.83 254,950.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 254,950.70