Dept. of Trans. PROGRESS Serial No. Contract No. 25-111-09-30 08-1H9914 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 79% Location: Federal Project: 08-VAR SSTG-000C(554) Progress payment No. 010 Payment period ending: 04-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,370,967.25 191,240.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 104,285.58 -40,127.00 4. Earned Subject to Retention 2,475,252.83 151,113.00 5. Mobilization 200,000.00 0.00 6. Total Work Completed 2,570,967.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,675,252.83 151,113.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 151,113.00