Dept. of Trans. PROGRESS Serial No. Contract No. 24-355-05-52 08-1H9924 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 69% Location: Federal Project: 08-VAR ACST-000C(552) Progress payment No. 004 Payment period ending: 12-20-24 GBA ENGINEERING INC 18543 YORBA LINDA BLVD 394 YORBA LINDA CA 92886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,274,122.10 403,756.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,274,122.10 403,756.60 5. Mobilization 195,000.00 9,750.00 6. Total Work Completed 1,469,122.10 7. Deductions -4,000.00 209,596.40 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,465,122.10 623,103.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 623,103.00