Dept. of Trans. SEMI-FINAL Serial No. Contract No. 20-273-12-48 08-1J1104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-RIV-10-12.8/124.2 NONE 08-RIV-79-40.4/40.4 08-RIV-86-R2.8/R11.9 Progress payment No. 013 Payment period ending: 06-23-20 VELARDE CONCRETE CONSTRUCTION INC 523 S. BRAND BLVD, #201 SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,310,557.03 0.00 2. a. Extra Work b. Adustment Comp. -38,780.62 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,271,776.41 0.00 5. Mobilization 293,782.00 0.00 6. Total Work Completed 2,565,558.41 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,555,558.41 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00